Erosion Restoration at Mill St.

Project Description

The City of Markham will be rehabilitating an erosion site just to the north of Mill Street as shown in the attached map. 

The site experienced a slope failure and loss of a street light in 2023 such that Mill Street was closed to traffic until permanent restoration is completed. 

Project Activities:

  • Installation of armor stone, rip rap and vegetated rock buttress;
  • Grading and topsoil application, installation of erosion control measures;
  • Street light installation;
  • Restoration of project area as per restoration plan and restoration details including Terraseeding and plantings and road surface restoration/rehabilitation; and,
  • Clean-up and restoration of the site after completion of the work.

Schedule

Construction is scheduled to commence in mid June 2024.


Mill St. Project Location

Contact Information:

Timothy Ng, P.Eng.
Project Engineer, Stormwater, Environmental Services Department
Tel: (905) 477-7000 ext. 2374
Email: tng@markham.ca