• 015-T-23 – Storm Culverts (SC04 & SC05 – Henderson Ave to Clark Ave (through Easement)
    • Initial pit completed off of Henderson Ave in Fall 2023
    • Relining of culvert occurring from June to Sept 2024
        • Excavation on Clark Ave has been avoided with changes to construction methodology

 

  • 289-T-23 – Markham Village Phase 1A – Storm Sewers and Watermain Upgrades
    • Storm sewer upgrades to be done
      • Church St (Maple St to Wootten Way N) – May to November 2024
      • Church St (Wooten Way N to 200m East of Rose Way) – May to October 2025
      • Jack Crt
      • Jill Crt
      • Judy Crt
      • Rose Way (Church St to Linden Lea St)
    • Watermain looping to be done
      • Jack Crt
      • Jill Crt
      • Judy Crt
    • Temporary asphalt restoration to occur in stages with road reconstruction works to occur in 2025
    • Construction is ongoing with anticipated completion in Fall 2025

 

  • Project # Pending – Markham Village Phase 1B – Storm Sewers and Watermain Upgrades
    • Storm sewer upgrades to be done
      • Wootten Way N (Church St to Sir Tristram Pl)
      • Sir Lancelot Dr (Wootten Way N to Sir Gawain Pl)
      • Sir Gareth Crt
      • Sir Kay Dr (Sir Lancelot Dr to Sir Gareth Crt)
    • Watermain replacement to be done
      • Wootten Way N (Church St to Ramona Blvd)
      • Sir Tristram Pl
      • Sir Gareth Crt (Watermain Looping at end of Court)
    • Construction is scheduled to start Spring 2025 with anticipated completion in Fall 2026

 

  • 009-R-24  – CIPP Watermain Lining Rehabilitation
    • Design work currently occurring for watermain structural lining on the following streets
      • Highway 7 (Cosburn Rd to Wootten Way)
      • Princess St (Rouge River crossing)
      • Tuclor Lane
      • Christman Crt
      • Green Lane (Guardsman Rd to Hunting Park Dr)
      • Guardsman Rd
      • Aileen Rd
      • Harlech Crt

 

  • 229-T-22 – West Thornhill Storm Upgrades – Phase 4B – Romfield Circuit and area
    • All storm sewer upgrades and road reconstruction completed by June 2024

 

  • 300-T-22 – Cast Iron Watermain Replacement – Drakefield Area
    • Watermain, services and restoration completed Fall 2023

 

  • 004-T-21 – West Thornhill Storm Upgrades – Phase 4A – Royal Orchard and area
    • All works completed for Storm and Sanitary Sewer upgrades
    • Top coat of asphalt installed in July 2023

 

  • 242-T-21 – West Thornhill Storm Upgrades – Phase 3C – Glen Cameron/Clark/Mira/Lilian/Pheasant Valley
    • All Storm Sewer, watermain and road reconstruction work completed by September 2023